Small modular reactors (SMRs) aim to change traditional nuclear power by using smaller, standardized units manufactured largely in factories and assembled on site. Typically defined by the IAEA as reactors up to about 300 MWe, SMRs are better seen as a family of approaches combining reduced unit size and modular construction; some designs (e.g., Rolls‑Royce) exceed that threshold. They use conventional nuclear fission but vary widely in technology—light water, high‑temperature gas, molten salt, and liquid‑metal fast reactors—so safety, waste, and operational characteristics differ by design. Many incorporate passive safety features that can simplify responses to incidents, but small size does not automatically mean lower risk or less stringent emergency planning.
The main promise is economic: lower upfront capital per unit, faster deployment, and the potential for cost reductions through serial manufacturing. However, industrial learning and mass production remain unproven at scale, and commercial success hinges on demonstrating timely construction, genuine cost declines, and resolvable licensing and waste-management challenges. Several projects are now operational, under construction, or licensed across Russia, China, North America and Europe, and interest from data‑center operators and Big Tech is growing. The coming decade will be decisive in proving whether SMRs can deliver on their economic and deployment promises.
SMRs promise to combine modular manufacturing, passive safety systems and less initial investment to rethink the role of nuclear energy. We analyse what they are, how they work, how much they cost and what projects are moving forward in 2026.
Building a conventional nuclear power plant requires a huge initial investment, lengthy regulatory processes and years of work. Small modular reactors, known as SMRs, want to change part of that logic.
The idea is to reduce the power of each unit, standardize the design, and move a much larger portion of manufacturing from the site to controlled industrial environments. The modules are then transported to the site for assembly.
The goal is to take advantage of industrial iteration to shorten lead times, reduce construction risks, and roll out capacity progressively.
The promise is important. The economic demonstration is still pending.
What are small modular reactors?
The International Atomic Energy Agency (IAEA) usually defines SMRs as advanced nuclear reactors with a power of up to 300 MW of electricity per unit, approximately a third of the capacity of a large conventional reactor.
The Spanish Nuclear Safety Council (CSN) also uses this threshold. The IAEA also maintains its ARIS database, which includes more than 80 designs in different stages of development and deployment.
There is, however, an important nuance. The SMR label is not used exactly the same in all countries and projects. Rolls-Royce SMR, for example, is developing a reactor called SMR in the United Kingdom with a capacity of 470 MWe, above the IAEA’s reference of 300 MWe.
That is why it is more useful to understand SMR as a combination of smaller scale and modular construction than as a perfectly closed category.
What does SMR stand for?
The acronym summarises their main characteristics: they are small, because they offer less power per unit than large nuclear reactors. And they are modular, because they seek to manufacture large parts of the facility off-site in a standardized way and then move them for assembly.
That also doesn’t necessarily mean transporting “the whole reactor” in a truck. Modularity varies greatly between designs. Rolls-Royce, for example, plans to manufacture about 90% of its plant in the factory and build the plant from around 1,500 transportable modules.
The physical principle is still nuclear fission. SMRs split atomic nuclei to release energy, just like today’s power plants. They are, therefore, very different from nuclear fusion, a technology that seeks to join light nuclei and which the Bankinter Innovation Foundation has analysed in Fusion Energy.
How an SMR works
In light water designs, the basic operation is familiar: the fission of uranium generates heat. That heat is produced and the steam moves a turbine connected to an electric generator. The novelty is mainly in the design of the installation, its scale and its manufacture.
Some SMRs integrate components into a single vessel that appear separate in a large plant. Others use refrigerants other than water or work at higher temperatures to produce, in addition to electricity, industrial heat.
This diversity explains why talking about “SMRs” as if they were a single technology can be misleading.
Are SMRs safer?
Many designs incorporate passive safety systems.
Instead of relying exclusively on pumps, electric generators or human intervention to keep the core cool in the event of certain incidents, they use physical phenomena such as gravity and the natural circulation of refrigerant.
The European Commission explains that these passive systems can increase the time available to respond to certain incidents and allow some active components to be dispensed with.
But an automatic conclusion should be avoided: small does not mean risk-free.
The specific design, fuel, refrigerant, location and decisions of the regulator are still decisive.
The same is true for emergency planning areas. Their possible reduction depends on the regulator’s design, safety analysis and assessment; It is not an automatic consequence of using a lower power reactor.
Not all advanced reactors are created equal
Under the SMR debate appear several technological families.
Light water reactors (LWRs) are the closest to current nuclear technology. Among them we find NuScale US460, GE Vernova Hitachi’s BWRX-300 or the ACP100, also known as Linglong One, which China is building in Hainan.
High-temperature gas-cooled reactors can reach temperatures that are particularly interesting for industrial processes. This includes the Chinese HTR-PM and X-energy’s Xe-100, an 80 MWe per module reactor capable of producing high-temperature heat and steam as well.
There are also designs cooled by molten salts. An important distinction should be made here. In some molten salt reactors, the fuel may be dissolved in the salt itself. But that is not the case with all designs.
Kairos Power, for example, is developing a high-temperature reactor cooled by fluorinated salts that uses solid TRISO fuel in the form of small spheres. Its coolant is a molten salt called Flibe.
Finally, fast reactors cooled by liquid metals such as sodium or lead appear.
One of the most advanced projects is Natrium, developed by TerraPower. Its sodium-cooled fast reactor will have a nominal power of 345 MWe and will be associated with thermal storage in molten salts. In terms of power and characteristics, it fits better into the broader category of Generation IV advanced reactor than into the IAEA’s strict definition of SMR.
How many SMRs are already working?
The commercial reality is still much smaller than the number of projects announced.
One of the first milestones was Akademik Lomonosov, the Russian floating nuclear power plant consisting of two KLT-40S reactors. It entered commercial operation in May 2020.
In China, the Shidaowan HTR-PM, consisting of two modules connected to a turbine, entered commercial operation in December 2023.
The next project to attract a lot of attention is ACP100 or Linglong One, a 125 MWe integrated pressurized water reactor.
It was scheduled to enter into operation in 2026. However, as of mid-September, it was still conducting pre-commissioning tests.
In the West, the project that has most clearly moved from blueprint to construction is GE Vernova Hitachi’s BWRX-300. Its first unit is under construction in Darlington, Canada, with completion scheduled for 2029 and commercial operation around 2030.
SMR vs. conventional nuclear reactor
| SMR Criterion | Conventional reactor | |
| Power | Typically up to 300 MWe per module | Often around 1,000 MWe or more |
| Construction | Greater degree of modularization and prefabrication | Much of the construction is done on-site |
| Investment per unit | Lower absolute outlay | Very high initial investment |
| Scalability | Possibility of adding modules | Capacity fixed from the project |
| Security | Many designs incorporate passive systems | Depends on the design and generation of the reactor |
| Commercial maturity | Very limited | Decades of operational experience |
The key economic difference is in the back row. Large reactors have decades of industrial experience. SMRs try to replace some of the economies of scale of a large plant with serial economies obtained by manufacturing many of the same units.
We do not yet know to what extent it will work.
The great challenge of SMRs: proving that the accounts work out
The main financial advantage of an SMR is not necessarily to produce electricity cheaper. It is to require a smaller investment per unit and allow capacity to be deployed gradually.
This reduces the amount of capital committed to each project and can be attractive to power companies, industries or grids that do not need reactors of more than 1 GW.
The outstanding issue is the cost per megawatt produced. Small reactors lose some of the economies of scale that favour large plants. To compensate for this, they need to manufacture many standardised units, reduce work on site and accumulate industrial learning.
The case of NuScale and its Carbon Free Power Project with UAMPS shows the risk. The project was cancelled in November 2023 after failing to get enough support among the participating municipal utilities.
That did not slow down the regulatory development of the technology. In May 2025, the US Nuclear Regulatory Commission approved the NuScale US460 design, consisting of six 77 MWe modules for a total of 462 MWe.
Approved technology does not yet mean economically proven technology.
How much does an SMR cost?
Here it is advisable to be especially cautious. There are estimates from manufacturers and numerous economic models, but very few finished commercial projects with which to compare them.
The SMR model is based on an industrial hypothesis: the first units will be more expensive, while the repeated manufacture of the same reactors should reduce the cost as the supply chain matures. The problem is that this learning curve has yet to be demonstrated.
That is why we avoid offering a single figure of “how much does an SMR cost”. The result depends a lot on the design, the country, the interest rates, the financing model, the regulation and, above all, whether we are talking about the first example or a hypothetical mass-produced fleet.
The BWRX-300, for example, proposes construction times of 24 to 36 months from the first nuclear concreting for mature or nth-of-a-kind units. It is a goal of the manufacturer, not yet an accumulated experience over a commercial fleet.
Waste remains a challenge
SMRs also do not eliminate radioactive waste: they generate spent fuel and other materials that must be managed over long periods, although their nature and quantity depend on the reactor and its fuel cycle.
Nor can it be said in a general way that, because they are small, they produce less waste per unit of electricity.
A study published in PNAS on the waste of three SMR designs concluded that certain designs can generate higher volumes of some waste per unit of energy produced than a conventional light water reactor. The authors themselves caution that their analysis studies three specific technologies and that the results should not be automatically extrapolated to all SMRs.
Waste management must therefore be evaluated on a technology-by-technology basis.
Companies and projects that are marking the career
The current map combines large industrial groups, state-owned nuclear companies and technology startups.
NuScale has a modular light water design approved by the US regulator.
GE Vernova Hitachi builds the first BWRX-300 in Canada, probably the most advanced Western project at the moment.
Rolls-Royce SMR advances programs in the United Kingdom, Czech Republic and Sweden with a 470 MWe PWR design based on modular manufacturing.
TerraPower obtained construction permit for Natrium in Wyoming in March 2026. It was a regulatory milestone for US advanced reactors.
X-energy develops the Xe-100. Its project with Dow in Texas is advancing in the regulatory process and the company is also working with Amazon and Energy Northwest on an initial deployment of four modules, expandable to twelve.
Kairos Power began construction of Hermes 2 in Tennessee in April 2026. The project will be its first demonstration plant capable of supplying electricity to the grid.
China continues to develop ACP100, while Russia keeps Akademik Lomonosov in operation and works on other advanced reactor concepts.
What happens with SMRs in Spain?
Spain does not currently have an authorized or ongoing SMR construction project. There is scientific and technological activity.
The Nuclear Safety Council is studying the regulatory challenges of SMRs, from the characteristics of their passive systems to the need to adapt certain licensing processes.
In addition, Spanish research groups have been involved for years in European projects related to their safety.
The Polytechnic University of Madrid participated in McSAFER, a European initiative aimed at developing advanced safety assessment methods for small modular reactors. Spanish research includes neutronic and thermohydraulic analysis, accident simulation and specific studies on designs such as NuScale.
Europe, on the other hand, has clearly accelerated its plans. In March 2026, the European Commission presented its strategy to accelerate the development and deployment of SMRs and advanced modular reactors. The aim is to make it easier for the first European projects to be operational by the early 2030s.
AI and Data Centers: A New Engine for Nuclear Power
The rapid growth of artificial intelligence has added a new element to the debate.
The International Energy Agency (IEA) estimates that global data center electricity consumption could reach about 945 TWh by 2030, more than double that of 2024 and slightly above Japan’s current electricity consumption. Artificial intelligence will be the main driver of that growth.
This demand explains why Big Tech is entering the nuclear debate.
Google has signed an agreement with Kairos Power to develop up to 500 MW of nuclear capacity through various reactors, with the first deployment planned around 2030.
Amazon has invested in X-energy and is supporting a first 320 MW project with Energy Northwest, expandable to 960 MW. X-energy and Amazon also plan to develop more than 5 GW of new capacity in the United States by 2039.
It is worth putting the calendars in perspective. The IEA itself estimates that the first SMRs responding to this new demand will start providing electricity around 2030.
AI is accelerating interest and investment. It is not yet being powered on a large scale by SMRs.
The future of small modular reactors
2026 marks an interesting time. The technology has moved beyond the purely conceptual phase. There are operational reactors in Russia and China, a BWRX-300 under construction in Canada, designs approved by U.S. regulators, and Generation IV projects that have already obtained construction permits.
Europe has also decided to accelerate. That doesn’t mean that the commercial promise is settled. The next projects will have to prove three things: that they can be built within the announced deadlines, that mass production actually reduces costs, and that new designs can overcome regulatory processes without losing the benefits of standardization. That’s where the real innovation lies.
SMRs try to transfer to the nuclear industry a logic common in other sectors: to manufacture the same product many times instead of building each plant as an almost unique project. If this logic works, they can open a new stage for nuclear fission.
If it fails to compensate for the economies of scale of large reactors, they will remain an attractive technology with an outstanding economic problem. The next ten years should provide a much clearer answer.
The Bankinter Innovation Foundation has already analysed this technology in The Future of Nuclear Energy: Compact Modular Reactors. Four years later, the difference is significant: some of those designs have made it to the construction sites, the licensing process and commercial contracts. The big test begins now.